Goodwood Aerodrome Building
Building information update
Building information update
The Aerodrome has presented us with a number of challenges since 2015 which means it needs wide-ranging remedial work to address defects. Work started on 6 November, and it is hoped that the building will be back and operational by early September 2018.
The Schedule
DATES | PROCESS |
November 2017 | Site established |
November 2017 to February 2018 | Preparation work, which includes taking off the current roof and installing temporary weathering. |
February to July 2018 | Internal work takes place |
February 2018 | Work to the external facade starts |
July to September 2018 | Internal finishing takes place which includes decorating, fixtures and furniture in place, testing, commissioning and snagging. |
July to September 2018 | External finishing takes place |
September 2018 | Aerodrome building opens |